Step 1
Dig out and base
We remove the soil, compact the red clay and lay crushed stone so the slab has something solid under it.













Raleigh · Cary · Apex · Durham · Morrisville · Wake Forest · Garner · Knightdale · Wendell

New driveways, two-car widenings, parking pads and long country driveways in Raleigh and the Triangle. We dig out, build a compacted base for the red clay, pour, finish and cut the joints. Clean broom or smooth finish: no stamped concrete.
What's included
How we do it
Step 1
We remove the soil, compact the red clay and lay crushed stone so the slab has something solid under it.
Step 2
Straight forms, the slope set for water, and steel reinforcement on chairs.
Step 3
Ready-mix concrete, spread and leveled while it is fresh.
Step 4
Floated, edged and broomed for grip in the rain.
Step 5
Cut straight so the concrete cracks where we want it, not across your driveway.
What you don't see
Tap each layer.
5 inches: cars, pickups and soft clay.

Surface
A broom finish gives grip in the rain; smooth or exposed aggregate where it fits. Never stamped: clean finishes last longer and are easier to repair.

4–6 in
4 inches is the usual minimum for cars; 5–6 inches for pickups, trailers, RVs or soft red clay. Thicker slabs carry more weight before they crack.

Inside the slab
Steel set on chairs so it stays in the middle of the slab, where it helps hold cracks tight.

Every 10 ft or less
Concrete always cracks a little. Joints cut about a quarter of the slab deep make it crack in a straight line, where you don't see it.

Compacted
A layer of crushed stone, compacted, so water drains and the slab sits on something solid, not on mud.

Carolina soil
North Carolina's red clay holds water and moves. Soft spots get dug out and compacted before anything goes on top.
Tool
400sq ft
5.3cu yd
4"thick
1truck
What parks on it?
Anything else?
Anything to remove?
Reference numbers, not a price. The estimate is free.
Photos
Tap a photo to see it big.
Questions

Walk on it after 1–2 days and park cars after about 7 days. Heavy trucks should wait about 28 days, when concrete reaches its design strength.
Another question? Ask Victor
4 inches is the usual minimum for cars. On soft red clay, or for pickups, trailers and RVs, 5 to 6 inches is the safer choice. We tell you what your job needs when we see it.
Another question? Ask Victor
Yes. The City of Raleigh requires a permit for new or replaced driveways, and the part by the street (the apron, in the public right-of-way) has extra requirements. Other towns have their own rules. Ask us and we will tell you what your job involves before we start.
Another question? Ask Victor
No. We focus on clean, long-lasting finishes: broom, smooth, exposed aggregate, and polished, stained or epoxy where it fits.
Another question? Ask VictorWe also do

Tear out the old one, pour a new one.

Back patios, grill pads and extensions.

Front walks, side paths and sidewalk sections.

Non-slip concrete around your pool.

Polished, stained, epoxy and sealing.
Text a photo of your driveway or yard and what you want done. Victor answers himself, in English or Spanish.